Latest News

 

           

The chip sealing will be completed by Fahrner Asphalt tentatively scheduled for the 3rd week or July 15th.  May vary due to weather. 

 

All vehicles will need to be removed from the street prior to the work being completed.  Please move your vehicle from the street if you see preparation activities occurring including no parking signs, door hangers, and other signage. 

 

The chip seal work entails sweeping, placing an emulsified sealer compound onto the street, and then overlaying it with fractured stone chips.  The chips will not be swept up immediately after the process to allow them to set into the sealer and compact into place.

 

It will be about a week until the stone chips are swept from the streets.  The area can be driven on immediately after placement with care; however, it is best to let the process dry for a couple hours before driving over. 

 

Please make the proper accommodations, if needed, for your own situation such as the moving of recreation vehicles or boats, the parking on a side street, rental notices, parking in rear, etc.

 

I apologize for the inconvenience.  This maintenance work is necessary to prolong the life of our streets.  Feel free to contact me with any questions.

 

Thank you,

 

Timothy D. Vergara, P.E.   

Administrator of Public Works


2019 Street Maintenance Work

No.

Street Location

Beginning Street

End Street

Type of Maintenance

1

Schmidt Avenue

Kamke Street

Frances Street

Boiler Slag Seal Coat

2

Becker Street

Frances Street

George Street

Boiler Slag Seal Coat

3

Peggy Lane

120' From Schmidt Ave

Previous Chip Seal Section

Boiler Slag Seal Coat

4

Lawrence Avenue

Frances Street

Arnold Street

Boiler Slag Seal Coat

5

Clark Avenue

Arnold Street

Laut Street

Boiler Slag Seal Coat

6

Yawkey Avenue

BUS 51

Third Street

Boiler Slag Seal Coat

7

Third Street

Jones Drive

Yawkey Ave

Boiler Slag Seal Coat

8

Second Street

Yawkey Ave

Wilson Ave

Boiler Slag Seal Coat

9

Everest Drive

BUS 51

First Street

Boiler Slag Seal Coat

10

Stonefield Trail

Weston Ave

Termini

Boiler Slag Seal Coat

11

Hemlock Ave

Stonefield Ave

Previous Chip Seal Section

Boiler Slag Seal Coat

12

Weston Avenue

Wilson Ave

250' W of Volkman Ave

3/8" Aggregate Double Seal Coat

13

Center Street

Weston Ave

Edgewood Ave

3/8" Aggregate Double Seal Coat

14

Douglas Street

Wall Street

Hemlock Ave

3/8" Aggregate Double Seal Coat